Short answer: You can measure dam depth with a fish finder by recording depth and position across the basin, correcting for the sensor’s mounting depth and documenting the water level. Estimating volume also requires shoreline information and a checked model of the bottom, not just the deepest reading.
A fish finder can help answer a different question from “how deep should I build my dam?” It records what is beneath the water now. Treat the result as a survey record with limitations, rather than assuming a colourful depth map is a certified storage figure.
Bathymetry is the measurement and mapping of underwater depth and bottom shape. The US Geological Survey’s Cannonsville Reservoir work combined depth measurements, positioning, water-surface elevations and a model of the bottom to calculate storage, illustrating why depth alone is not enough (USGS survey methods).
How do you measure dam depth with a fish finder?
Start by checking what the instrument can record, not only what its screen displays. Sonar is a method of measuring underwater distance using sound echoes. A transducer is the sensor that sends and receives those sound signals. A sounding is an individual recorded depth measurement, ideally paired with its position and the survey time.
For the GPSMAP models covered by Garmin’s manual, Quickdraw contour recording requires sonar depth, GPS position and a memory card with free space (Garmin GPSMAP manual). Check your own model’s recording and export options before travelling to the dam; a live depth display is not proof that usable survey data will be saved.
The sensor’s position matters because a reading measured below the transducer is not automatically the full distance below the water surface. Garmin distinguishes installation corrections from other mapping adjustments, with settings dependent on the transducer’s location (Garmin depth-offset instructions). Measure the installation, follow the exact model’s sign convention and record the setting rather than guessing whether to add or subtract.
Which water level should a fish finder survey use?
Choose and document a consistent reference before comparing readings. A datum is a defined reference level against which elevations are measured. An offset is a correction applied to a reading or mapped level. Keep the sensor’s mounting correction separate from any correction for changing water level.
Garmin’s Quickdraw example uses a previous depth of 3.1 m and a current depth of 3.6 m at the same location, giving a recording offset of -0.5 m (Garmin recording-offset example). That is the manual’s example, not a universal setting for every fish finder.
Photograph a stable reference mark and record the water level against it at the start and finish. Note pumping, inflow or other changes during the survey. If separate visits use different reference levels, do not compare their displayed depths as though the difference must represent a changed bottom.
| Record | Check before interpreting it |
|---|---|
| Sensor mounting depth (m) | Confirm what the displayed and exported depths are measured from. |
| Water level at each visit (m) | Use the same documented reference, not an estimated old waterline. |
| Position and depth files | Confirm the saved data can be reopened and used outside the live display. |
| Unmeasured shoreline areas | Identify gaps rather than letting a smooth map conceal them. |
| Repeat measurements | Investigate disagreements before accepting the model. |
How do you collect useful survey coverage?
Plan coverage across the basin rather than following a convenient circuit around its edge. A transect is a planned survey line across the water. The USGS survey used planned lines and separate oblique check lines to assess its bathymetric work (USGS field survey description). For a farm dam, ask the survey provider how their line layout will capture narrow arms, shallow shelves and changes in slope.
There is no spacing recommendation here that suits every basin or instrument. Request a coverage plan matched to the purpose of the work, and agree how inaccessible edges will be represented. Keep a copy of the actual tracks, not only the finished coloured map.
- Define whether the survey supports general storage planning, a repeat comparison or a professionally specified design task.
- Confirm safe access, suitable equipment and a competent operator before arranging work on the water.
- Record the water-level reference, sensor installation and instrument settings.
- Plan basin coverage and independent checks, identifying areas that cannot be measured safely.
- Save the original readings, track files, photographs and notes before leaving the site.
- Review gaps and inconsistent readings before producing a volume estimate.
Do not enter the water to retrieve a sensor or collect a manual reading. If safe access cannot be arranged, stop and commission suitable survey assistance. Our farm dam water-safety guide discusses water-entry risks; owning a fish finder does not make the dam a suitable boating or swimming site.
How does a depth map become a dam volume estimate?
A volume estimate needs the extent of the water as well as depths across it. Keep the shoreline measurement tied to the same water level as the depth survey. Our guide to measuring a dam’s surface area covers that separate part of the job.
Interpolation is the estimation of values between measured points. A bottom-surface model uses the survey observations to represent underwater shape, with interpolation across gaps; USGS used such modelling to produce an elevation, area and capacity table (USGS capacity modelling). Ask which parts of your result are measured and which depend heavily on assumptions.
The Northern and Yorke Landscape Board guide converts cubic metres to megalitres by dividing by 1,000: 1,000 m³ equals 1 ML (South Australian dam-management guide). Keep those units visible on every estimate.
The same guide gives the shortcut 0.4 × surface area × maximum depth, with area in square metres and depth in metres, to estimate volume in cubic metres (Landscape Board volume estimate). Treat that shape allowance as a rough estimate, not as a substitute for a surveyed irregular basin.
Request the result at the measured water level first. A figure for a higher operating level needs information about the basin above today’s waterline, while a lower-level estimate needs enough detail around the remaining pool. State the reference level beside the volume so the number can be interpreted later.
What can the survey miss?
A smooth display can hide sparse observations. A contour is a line joining points with equal depth or elevation. Do not judge survey quality from the number of contour lines on the screen; ask for the observations, checking method and limitations that support them.
USGS produced Cannonsville Reservoir contours at 2-foot intervals and capacity values at 0.01-foot elevation intervals (USGS published survey outputs). These are output intervals for that project, not proof of equivalent measurement accuracy or specifications for a farm survey.
Do not label a consumer sonar return “original excavated floor” or claim a silt thickness without evidence identifying those surfaces. Likewise, do not diagnose a leaking wall from a depth map. Record uncertain bottom readings as unresolved observations and ask what additional investigation would establish the answer.
Garmin expressly cautions that it makes no representation about the accuracy or completeness of maps generated by third parties (Garmin mapping limitations). Keep a distinction between an owner’s useful planning record and a survey commissioned for an engineering, contractual or regulatory decision.
When should you commission a professional survey?
Commission appropriate survey advice when a decision depends on a defensible volume, repeatable comparison or excavation quantity. Tell the provider the intended use before they price the work. Ask them to specify coverage, position and depth checks, reference levels, deliverables and the uncertainty they can reasonably support.
In the 2020 Razorback Mountain repair account in NSW, Big Ditch’s Lindsey Hughson described working the final four tonnes of bentonite into a leaking wall and completing the remaining work despite wet, slippery conditions (Razorback Day 5 project account). Bentonite is a clay used in dam sealing; the account documents repair work, not a sonar survey or a measured storage-capacity claim.
Keep that distinction when planning your own work: a depth survey answers questions about the basin, while a repair proposal needs evidence about the defect. Send Big Ditch your existing plans, water-level notes, photographs and survey files through our site-inspection enquiry form. Explain the decision you need to make so the inspection can address the missing information.
Frequently asked questions
Can a fish finder measure silt thickness?
Do not assume a depth display measures silt thickness. For that purpose, ask a suitably qualified survey or investigation provider to explain how they will identify both the sediment surface and the underlying boundary. Request evidence for the interpretation, and keep any unverified thickness out of excavation quantities. A familiar-looking bottom trace is not enough to establish which material boundary it represents.
Can I compare surveys taken at different water levels?
Yes, but first establish a common reference and check that the instrument settings and saved data are comparable. Garmin provides a recording-offset method for its Quickdraw system, distinct from other offset settings (Garmin survey-offset guidance). If the earlier water level or configuration is unknown, treat a comparison cautiously rather than attributing the difference to sediment accumulation or excavation.
Is a fish finder map enough for excavation quantities?
Do not use an unchecked consumer map as the sole basis for a priced excavation quantity. Ask the surveyor and contractor to agree the surfaces being compared, the measurement method and the uncertainty before quantities enter a contract. Keep the original files and assumptions with the estimate. A displayed storage volume and the volume of material to remove are different questions, requiring separately defined boundaries.
Need to measure dam depth before planning repairs? Book a site inspection with Big Ditch to discuss the evidence your dam assessment needs.


Practical dam advice, straight to your inbox
Get an email when Big Ditch publishes a new article about dam construction, repairs or water management.
Get dam updates
Confirm your email to subscribe. Unsubscribe at any time. Privacy Policy